Jump to content


Photo

MARTA to renovate Five Points station


  • Please log in to reply
6 replies to this topic

#1 KevinKorell

KevinKorell

    Board Leader

  • Sr. Admin
  • PipPip
  • 83037 posts
  • Gender:Male
  • Location:Lakewood, NJ
  • Interests:Making America TRAIN again!

Posted 24 June 2021 - 09:42 PM

Atlanta, GA Journal-Constitution, 6/24/21:

 


 

     $150 million renovation of MARTA’s Five Points station moving forward  

 

 

MARTA is moving forward with the $150 million renovation of Five Points station in downtown Atlanta.

 

Details



Kevin Korell


OTOL Board Leader


Lakewood, NJ


#2 KevinKorell

KevinKorell

    Board Leader

  • Sr. Admin
  • PipPip
  • 83037 posts
  • Gender:Male
  • Location:Lakewood, NJ
  • Interests:Making America TRAIN again!

Posted 09 June 2024 - 02:05 PM

WSB-TV, Channel 2 in Atlanta, GA, 6/6/24:

 


 

  MARTA plans to limit access to Five Points Station in downtown Atlanta for up to 4 years      

 

 

MARTA is getting pushback on plans to close access to the Five Points station in downtown Atlanta for up to four years.

 

Story



Kevin Korell


OTOL Board Leader


Lakewood, NJ


#3 KevinKorell

KevinKorell

    Board Leader

  • Sr. Admin
  • PipPip
  • 83037 posts
  • Gender:Male
  • Location:Lakewood, NJ
  • Interests:Making America TRAIN again!

Posted 09 June 2024 - 02:08 PM

Urbanize Atlanta,  5/29/24:

 


 

   MARTA's $230M Five Points station overhaul sets start date  

 

 

Significant changes are in store for MARTA’s largest and busiest transit station, beginning in about five weeks.

 

 

This story



Kevin Korell


OTOL Board Leader


Lakewood, NJ


#4 KevinKorell

KevinKorell

    Board Leader

  • Sr. Admin
  • PipPip
  • 83037 posts
  • Gender:Male
  • Location:Lakewood, NJ
  • Interests:Making America TRAIN again!

Posted 09 June 2024 - 02:09 PM

Axios, 6/7/24:
 

     Atlanta mayor calls for time-out on $230 million Five Points overhaul  

 
 
 
Mayor Andre Dickens wants MARTA to halt a $230 million overhaul of the transit system's Downtown hub until after an audit of the agency is complete.

 
 
More


Kevin Korell


OTOL Board Leader


Lakewood, NJ


#5 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43971 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 12 June 2024 - 07:09 AM

WANF-TV (Atlanta News First), Atlanta, GA  6/10/24

 

Atlanta mayor to MARTA: Stop $230 million Five Points expansion until audit complete

 

 

Andre Dickens tells transit CEO several areas need more ‘clarity, attention.’

 

ATLANTA, Ga. (Atlanta News First) - Atlanta Mayor Andre Dickens is requesting MARTA to halt its plans for a massive Five Points rail station expansion until an audit is completed.

 

In a letter dated June 6, 2024, Dickens told MARTA CEO Collie Greenwood an operational audit conducted by Mauldin & Jenkins “highlight several areas that require additional clarity and attention.”

 

“My team and I are in the process of reviewing these initial findings and we anticipate receiving the final report by late July,” Dickens wrote. “Given the significance of the insights expected from this report, I am requesting that MARTA temporarily halt the Five Points MARTA station project until we are in receipt of the final report and engage in subsequent discussions together to determine the best possible path forward for MARTA and the City of Atlanta.”

 

 

Continue here with video report.



#6 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43971 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 12 June 2024 - 07:14 AM

WANF-TV (Atlanta News First), Atlanta, GA  6/10/24

 

 
MARTA responds to Atlanta mayor, says Five Points station renovation plan will not stop

 

ATLANTA, Ga. (Atlanta News First) – On Monday, in what’s become a letter-writing battle, MARTA’s CEO told Atlanta’s mayor that MARTA has no intention of stopping their renovation plan at the Five Points station in downtown Atlanta.

 

“Successful execution of any and all public construction projects requires thoughtful planning on the front end, robust public engagement throughout the process and fortitude to advance the project to completion,” said MARTA CEO Collie Greenwood, in a letter sent to Atlanta Mayor Andre Dickens on Monday afternoon.

 

SNIP

 

In Monday’s response, Greenwood explained to the mayor that the renovation plan designs were already approved by both the city and the MARTA board and that contracts had already been ushered through.

 

“We have worked through all necessary agreements with our partners at the Federal Transit Administration/USDOT and have signed contractual obligations with multiple contractors,” Greenwood wrote in the letter.

 

Greenwood said the audit concerns should not be a reason to halt the construction project.

 

 

More here with video report.  



#7 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43971 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 23 June 2024 - 07:02 AM

WANF-TV (Atlanta News First), Atlanta, GA  6/21/24

 
Riders, transit advocates push for keeping access point open during Five Points MARTA station renovation

 

MARTA says it is working to limit the disruption to the public

 

ATLANTA, Ga. (Atlanta News First) - MARTA is standing firm on plans to transform one of its busiest stations.

 

While the project will take years, MARTA officials say the street level will not be closed off for four years like some have suggested. The transit agency stressed that the plan is to have the street-level access to its Five Points station closed for about 18 months.

 

The major renovation of the Five Points station has had pushback from residents and city leaders. Some in Atlanta continue to sound off on the upcoming street access closure that is set to start July 29.

 

 

Continue here






1 user(s) are reading this topic